DPU approves attributes-only Round 2 83E Procurement: ISC status in future procurements deferred to future stakeholder discussions

In May 2026, as discussed in Part I and Part II of our Section 83E Round II Series, the Massachusetts Department of Energy Resources (DOER) and the electric distribution companies (EDCs) divided on whether to propose an Indexed Storage Credit (ISC) framework in their Draft Request for Proposals (RFP) that would have introduced an Energy Services contract structure, potentially expanding the possible participation pathway for non-Clean Peak Standard (CPS) resources. They haven’t closed the door to this mechanism yet for future procurements, and they are looking for further analysis before allowing such structure to move forward.
This blog post discusses the final treatment of those issues by the Department of Public Utilities (DPU), the resulting Environmental Attributes-only Round II solicitation, and the implications for bidders and future Massachusetts storage procurements.
Background: On July 27, 2026, the Massachusetts Department of Public Utilities (DPU) issued an Order in Docket 26-75 partially approving the timetable and method proposed by DOER and the EDCs for Round II of the 83E Solicitation. The DPU approved a procurement for clean peak energy credits (CPECs), but directed DOER and the EDCs to remove all provisions related to the proposed ISC and Energy Services framework. However, DPU did not determine that an ISC was unauthorized under Section 83E. Instead, it deferred consideration of an Energy Services mechanism while DOER and the EDCs further develop the concept for a potential future procurement.
Consistent with the Order, DOER and the EDCs published the Final RFP on July 31. The Final RFP seeks up to approximately 1,000 MW of mid-duration (defined as 4-10 hours) energy storage capacity through long-term contracts. Eligible projects must achieve commercial operation by December 31, 2032. The solicitation also includes a nonbinding target of 250 MW to 300 MW for distribution-connected projects.
DPU Defers the Energy Services and ISC Question: For all RFPs following Round I, the Section 83E requires each procurement to consider Environmental Attributes, Energy Services, or a combination of both. DOER supported including the ISC as a means of providing a broader revenue hedge and creating a participation pathway for resources that may not qualify to generate CPECs. As noted above, the EDCs opposed its use in Round II, citing unresolved legal, technical, modeling, and cost-recovery concerns.
DPU ultimately determined (in line with the EDCs’ preferences) that Section 83E requires consideration of Energy Services but does not require every solicitation (following the first one, which was required to be attribute-only) to procure them. DPU also declined to determine whether the ISC as initially proposed for Round II satisfies the statutory definition of Energy Services, finding that the record was not sufficiently developed to evaluate the competing positions of DOER and the EDCs, or compare the ISC with alternative structures.
To enhance the record, DPU ordered DOER and the EDCs to continue evaluating the ISC or other Energy Services mechanisms and submit joint progress reports on October 30, 2026, January 29, 2027, and March 31, 2027; stakeholder engagement is expected.
Based on the Order, it is clear that for DPU to approve an ISC structure for a future procurement round, any future proposal must include a more complete explanation of how the reference energy value is calculated, how the settlement would perform under different market conditions, how ratepayer benefits would be measured, and how EDC cost-recovery risk would be addressed. The stakeholder process will also need to consider whether non-CPS-eligible projects should participate and what public benefits should be required from existing resources receiving long-term revenue support.
Final RFP/CPEC Pricing Implications: With the Energy Services provisions removed, bidders must propose fixed annual prices for CPECs or other eligible Environmental Attributes. Payments will be based on attributes delivered under the contract. CPEC prices are capped at 97.75% of the applicable CPS Alternative Compliance Payment (ACP) — $65 per CPEC from 2026 – 2032 and $45 per CPEC from 2033 – 2050.
Round I provides the first observable benchmark for Section 83E Environmental Attribute contract pricing, with selected project prices ranging from $20.40/CPEC to $36.40/CPEC. However, the Round I contracts are not directly comparable. Trimount ($36.40/CPEC) and Salt Cod ($20.40/CPEC) sell 100% of contracted CPEC output for 20 years, while Energizar ($32.75/CPEC) sells 80% of its CPEC output for 12 years. Projects also differ in size, location, interconnection exposure, development schedules, and financing assumptions.
The Environmental Attributes-only structure is also easier to administer than the proposed ISC because settlement is tied to delivered attributes rather than a modeled energy-market reference value. That said, developers (as in Round I), will continue to bear merchant exposure associated with energy, capacity, and ancillary services revenues. A fixed CPEC contract can reduce uncertainty around Environmental Attribute revenue, but it does not stabilize the project’s broader market earnings.
The CPEC-only structure may also affect bid pricing and financing. Since developers retain merchant exposure to energy, capacity, and ancillary services revenues, bidders may incorporate a greater risk premium into their proposed CPEC prices than under a broader revenue hedge such as an ISC. Simply put, if less revenue is hedged, the resulting increase in project risk could be reflected in higher financing costs and, in turn, higher bid prices. That said, the overall impact on ratepayer costs relative to an ISC is uncertain and depends on the magnitude of that risk premium and the foregone monetized wholesale market-derived benefits.
The firm December 31, 2032 commercial operation deadline may represent one of the most consequential risks in the Final RFP. To this end, bidders must demonstrate credible schedules for permitting, interconnection, financing, equipment procurement, construction, and testing. At the same time, recent Transitional Cluster Study results indicate that certain required network upgrades could take years to complete, materially constraining the ability of affected projects to achieve commercial operation by 2032 and leaving limited room for restudies, permitting delays, supply-chain constraints, or construction setbacks. Once we have analyzed the results we will provide a follow-up Blog Post on the impacts of the final results of the TCS. As a result, projects with substantial interconnection exposure may need to incorporate additional schedule, cost, and financing risk into their CPEC bids, while some projects may ultimately determine that the required commercial operation date is not achievable.
This risk was already made plain in the final set of contracted projects in Section 83E Round I. Rhynland Energy’s 500 MW River Mill Storage project, which DOER selected in December 2025, was not included in the initial group of executed contracts submitted to the DPU after Rhynland requested additional time to evaluate interconnection upgrade cost estimates identified through ISO-NE’s Transitional Cluster Study process. The project’s experience illustrates how unexpectedly high interconnection costs and uncertain upgrade timelines can affect contract execution and project viability even after a project has been selected through a Section 83E procurement.
Distribution-Connected and Existing Projects: Round II expands the Section 83E framework by allowing distribution-connected projects to participate. The Final RFP includes a 250 MW to 300 MW procurement target for those projects, although the target is not a carve-out and the Selection Team is not required to select any particular amount of distribution-connected capacity.
The DPU approved the proposed >1 MW minimum bid size and applicable site-control requirements for Distribution Projects, while allowing bidders to submit multiple Distribution Projects as part of a portfolio and to establish contingency relationships among those proposals. It also declined to provide additional scoring weight for distribution-connected resources.
In addition, distribution-connected projects participating in an applicable EDC tariff, flexible interconnection offering, pilot, or similar program remain eligible if they satisfy the RFP’s operational and contractual obligations. This clarification appears intended for projects participating in National Grid’s Active Resource Integration pilot. However, we note that other provisions of the Round 2 RFP exclude solar-plus-storage projects participating in the Solar Massachusetts Renewable Target (SMART) program, and selected distribution-connected projects must accept standard, non-negotiable long-term contracts.
In its order, DPU also confirmed that existing storage systems may compete if they can provide the product being solicited and satisfy the applicable threshold requirements, and do not need to demonstrate that a contract is necessary to support initial project financing, and requirements such as site control may not apply in the same manner to an operating resource.
The practical issue for existing projects is product eligibility. A facility that began operating before January 1, 2019, and has no eligible incremental capacity cannot generate CPECs and therefore has no Environmental Attribute to offer in this procurement. New incremental capacity at an existing facility may still qualify if it satisfies the applicable requirements.
We note, though, that the decision to defer the potential ISC to future procurement rounds narrows the commercial pathway for non-CPS-eligible resources, including certain existing pumped-storage facilities. Those projects are not excluded solely because they already operate. Their ability to compete depends on whether they can deliver an eligible CPEC. A future Energy Services structure could reopen participation for a broader group of existing resources, but the terms of that participation remain unresolved.
Evaluation, Interconnection, and Contract Process: The DPU approved the proposed allocation of 75 points to quantitative criteria and 25 points to qualitative criteria but declined stakeholder recommendations to place greater weight on qualitative factors, deciding to defer to the Evaluation Team’s determination that the 75/25 split is appropriate.
Economics will remain the principal scoring factor, although qualitative criteria may affect rankings where proposals have similar evaluated costs. Interconnection progress is also likely to receive significant attention. A low-priced bid may still be disadvantaged if its upgrade assumptions, queue position, or commercial operation schedule are not credible.
DPU approved the use of surplus interconnection service (SIS) where the original interconnecting customer receives Capacity Network Resource Interconnection Service (CNRIS). DPU also declined to require a separate public review of the transmission-connected form contracts before Round II proceeds. It found that bidders will have opportunities to raise substantive issues during negotiations and in the later DPU contract-approval proceedings.
Finally, for distribution-connected projects, the DPU found the EDCs’ separate stakeholder review of the form contract documents sufficient for Round II. For future solicitations, the EDCs must provide transmission-connected form contracts to the Independent Evaluator at least two weeks before filing a draft RFP and must file the non-negotiable distribution-connected contract with future draft solicitations.
Schedule: The Final RFP establishes the following schedule:
| Event | Anticipated Date |
| Final RFP issued | July 31, 2026 |
| Bidders’ conference | August 13, 2026 |
| Deadline for bidder questions | August 20, 2026 |
| Confidential and public proposals due | September 10, 2026 |
| Project selection and commencement of negotiations | January 27, 2027 |
| Execution of long-term contracts and Memoranda of Understanding with DOER | April 28, 2027 |
| Submission of long-term contracts to the DPU | May 26, 2027 |
The period between issuance of the Final RFP and the proposal deadline is relatively short. Bidders will need to finalize pricing, interconnection assumptions, financing plans, development schedules, and threshold documentation before September 10.
Conclusion/Next Steps
The Final Round II RFP advances Massachusetts’ storage procurement program under a contract structure that is familiar to bidders and easier to implement within the current schedule. It confirms the eligibility of distribution-connected projects, establishes a nonbinding distribution target, preserves participation for existing systems that can deliver eligible attributes, and maintains the December 31, 2032, commercial operation deadline.
The policy work now shifts toward Round III. The October 2026, January 2027, and March 2027 progress reports will indicate whether DOER and the EDCs are developing an ISC or another Energy Services structure that can address financing needs, statutory requirements, ratepayer protections, and the treatment of non-CPS-eligible resources.
Massachusetts has chosen the simpler procurement structure for Round II. The remaining question is whether the stakeholder process can produce a broader storage revenue product that is sufficiently developed for the next solicitation.
Want to know what the Round II decision means for the CPEC price outlook? CPMO subscribers have access to our updated CPEC forecast, including our new Round II Base Case and analysis of the factors that could affect future CPS supply-demand balances and CPEC prices. To learn more about CPMO subscription offerings and Massachusetts Clean Peak and storage market analysis, please contact Bob Grace, Jim Kennerly, or Madeline Frierson.




